Separate materials from works
The stone specification records type, format, finish and quantity. The works plan records removal boundaries, base, drainage, barriers and restoration. They are separate documents with separate responsibilities.
| Planned activity | Check before supply |
|---|---|
| Private-courtyard receiving | gate, area and unloading |
| Footway removal | owner and approval for works |
| Earthworks | current permit procedure |
| Temporary storage | lawful safe location |
| Restoration | material, schedule and responsible contractor |
Compare split setts, sawn paving and slabs. Agree kerbs with levels and drainage.
NIKA GRAN does not claim an office, warehouse or completed projects in Mykolaiv. Current route feasibility, vehicle, price and date are checked for the request.
Frequently asked questions
Is permission needed if stone is only delivered into a courtyard?
Not automatically, but equipment and packages must remain on lawful land.
Who obtains permission for earthworks?
The current procedure and contractor agreement decide it; the product supplier is not automatically the applicant.
When should production start?
After the specification and a realistic receiving and works schedule are approved.
Paving catalogue · Send the technical brief
Source clarification, 15 October 2026. Decision No. 32/36 of 1 April 2005 was repealed by clause 2 of Decision No. 12/21 of 19 April 2007. The linked 2007 decision includes amendment links, but the availability of that publication does not establish current legal validity of every provision or completeness of the consolidated text. Before work, confirm applicable requirements and any permit with the responsible city authority. This article is not a legal opinion.
Sources
- Mykolaiv City Council: earthworks without permission
- Decision No. 12/21 of 19 April 2007 — successor to the repealed 2005 decision
- NIKA GRAN delivery terms
Checked 14 October 2026. Confirm permits and route on the order date.